Statement of expenditure incurred on the
Extension to Kai Tak Airport.
(The area is shown cross hatched on accompanying plan.)
1. Contract No.17/1935.
Filling, levelling, bridging, Flight Gap $123,699.14
Deduct cost of filling between x and y
2.
on plan
Contract No.42/1937.
Formation, Sai Kung Rd., Contract $28,853.06
Departmental charges including
1.729.98
$121,969.16
Waterworks and drainage charges
11.568.30
$40,421.36
Roads Office. Maintenance Contract.
Surfacing road, Flight Gap, including Waterworks and drainage charges Surfacing Sai Kung Rd., from Sam Tack Road to Flight Gap, including drainage charges
24,573.74
10.103.57
$75,098,67
Deduct cost of work carried out between x and y on plan
25.947.11
$49,151.56
3. Electrical Office, departmental charges
153.30
4. Resumptions, P.W.D.
5. Salaries and Supervision.
Proportion chargeable to extension,
between y and z on plan, estimated at
Air Ministry contribution, half cost = $141,500
98.620.48
$269,894.50
13.105.50
$283,000.00
Less paid 26.8.37
100.000
Amount now payable
$41.500